In 2014, construction of a new kindergarten began in Tas-Yuryakh settlement - an event that young families still remember to this day. For a small settlement, such a project means more than «one more building»: it is a certainty that the settlement is developing, that children will not have to grow up on a waiting list and temporary solutions.

But the joy did not last long. Already in 2015, the construction was frozen. And this is precisely the case when the problem was not in need and not in the lack of money, but in contractors and deadlines: construction was started, but the project was not completed.

In 2017, at the request of the Mirny District Administration, RNG JSC provided 300 m³ of inert materials for backfilling the adjacent territory of the of a kindergarten in Tas-Yuryakh settlement.
Tas-Yuryakh kindergarten long building contractors funding ALROSA RNG 2017
The material is part of the TRK-ALROSA archive on OERN. At the bottom there is a block «Related materials» to go to neighboring stories.

Project Chronology

2014
Start of construction
2015
Work freeze
Auctions
Change of contractors
Entry deadline
Postponement to 2018

Zoya Danilova, the head of the Botuobuyinsky Legacy Municipality, explained: in 2014, the first auction was held, and Mirnystroy won, but the deadline was missed and the contract was terminated. Then a new auction was held, and the winner was the company Kridstroy.

The essence of the problem: the construction site became the most famous long construction project in the village not because of lack of funds, but because of the fact that contractors started work and did not bring the facility to commissioning, contractors started work and did not bring the facility to completion.

Funding and participants

The construction is financed by ALROSA, Mirny District Administration and Taas-Yuryakh Neftegazodobycha. Separate assistance is provided by the joint-stock company RNG.

Evgeny Cherikaev, Deputy General Director - Chief Engineer of RNG JSC: «The administration of the Mirny district asked RNG JSC to provide 300 m³ of inert materials for backfilling the adjacent territory of the kindergarten in Tas-Yuryakh settlement».
Fact (2017): 300 m³ of inert materials were provided for backfilling the adjacent territory of the kindergarten.

What was ready

Parameters

  • design capacity: 50 seats
  • project cost: over RUB 40 mln

Equipment

  • the necessary furniture and equipment have already been purchased
  • Commissioning dates postponed; plan shifted to 2018

Creedstroy had planned to commission the kindergarten back in early October, but the deadline was postponed again - to 2018.